if 15 workers complete a piece of work in 18 days in how many days will 27 workers complete the same work?​

Respuesta :

Аноним Аноним
  • 26-04-2021

10 days is your answer

Answer:

15 workers =18 days to complete work

1 worker =18×15=270 days to complete work

27 worker=270/27=10 days to complete work

Answer Link

Otras preguntas

Please help explain how to solve this. Find the value of each variable.
I need help with my PBA can someone please help me write a 3 paragraph PBA Do you think Shakespeare teaches us about ourselves and the world? Use appropriate e
14. Write the linear inequality shown in the graph. A. [tex]y\geq -3x+5[/tex] B. [tex]y\geq -3x-5[/tex] C. [tex]y\leq -3x+5[/tex] D. [tex]y\leq -3x-5[/tex]
Look at these lines: ‘Suddenly I heard high-pitched screams. “No-o-o-o!” screamed the scream. “No! No! No!” The crowd froze. Every single person turned towards
Chemical changes are changes that involve a change in the chemical identity of a substance. In other words, a new chemical or substance is created through a che
help help help plz i suck at this
What is the surface area of the box below? Height = 4 inches Width = 4 inches Length = 8 inches
heyy! i’ll give brainliest please help thanks
nd 90% of people marry there 7th grade love. since u have read this, u will be told good news 2night. if u don't pass this on nine comments ur worst week starts
Which of the following statements is true about Mexico, Brazil, AND Cuba? A. Most people live along the eastern coast of the country. B. Most people live in