seven people need 90 days to repair and paint a heritage building.if the job should be completed in 15 days.how many more people need to be employed.​

Respuesta :

khababnazir10
khababnazir10 khababnazir10
  • 22-11-2019

Answer:

Here is your answer mate

Step-by-step explanation:

As we know that 7 person take 90 days so 1 person takes 90×7=630 days

As work has to be finished in 15 days than 630/15=42 so

42 people can complete work in 15 days but as we have already 7 people employed so required are

42-7=35 so 35 more are needed

Answer Link

Otras preguntas

A textbook store sold a combined total 402 of psychology and math textbooks in a week. The number of psychology textbooks sold was two times the number of math
Which of the following has the greatest number of particles A) 1 mole of Na B)22.990g of Na C) 1 mole of Be D) 9.012 g of Be E) all are the same
In a study on the effect of music on worker productivity, employees were told that a different genre of background music would be played each day and the corres
why does photosynthesis occur even in light that is not absorbed by chlorophyll? ​
Integrals with variables.
which of the following will not disqualify your car from being used for the class E driving skills test
At Keller’s bike rentals it costs $21 to rent a bike for 4 hours How many hours of bike use does a customer get per dollar Round answer to nearest hundredth
please help. (sources of information(​
Part A - Name and describe the chemical process producers use to make glucose and the chemical process used by both consumers and producers to make ATP to contr
I’m very bad at angles, please help